As an existing contractor for Stretford Mall Shopping Centre, we have been part of the redevelopment works at Stretford Mall Shopping Centre initially carrying out realignment works to ensure that the area of demolition does not effect the remaining electrical installation.
This included:
- Installation of new sub distribution boards and sub main cables installation of new electrical lighting to relocated services room.
- Re-routing electrical supplies.
- Stripping out the electrical installation in the area’s ready for demolition.
These works have continued into preparation ready for the new entrance area to be built and we are looking forward to working with the main contractors onsite to deliver this exciting new entrance.